THE BUILD RECAP / TIME-LINE
Pre-petit work list items: 190
Acura ARX-02a Statistics:
Chassis mechanical parts: 4000
Chassis electrical parts: 250
Engine parts: 100 (excluding internals of engine)
Gearbox parts: 350
Parts with tracked life: 1000 (excluding internals of engine)
Custom hardware (fasteners, o-rings, bearings): 450
Rebuild Statistics:
Parts reused: about 10%
Rebuild Timeline
(times are when tasks were completed, unless otherwise noted)
Thursday
3:43 PM - Accident
4:15 PM - Damaged assessment finished
4:45 PM - Spare part serial numbers allocated for car build
5:00 PM - Finalized arrangements to ship spare tub
6:00 PM - Spare tub picked up by freight service in California
6:45 PM - Damaged car stripped, reusable parts identified
11:00 PM - Replacement parts prepared and arranged for assembly
12:00 AM - Team back to hotel
Friday
7:10 AM - Spare tub arrives at Atlanta airport, met by team members
7:30 AM - Breakfast
8:00 AM - Begin preparation for car build, organize and layout assemblies
9:30 AM - Spare, bare tub arrives at track
11:00 AM - Tub preparation finished
12:00 PM - Lunch
11:30 PM - Fresh engine fitted
1:30 PM - Fresh gearbox fitted
6:00 PM - Dinner
8:00 PM - Four corners fitted on car
9:00 PM - Race spare preparation begins
11:45 PM - Hydraulic/fuel/electronic systems tested
Saturday
1:00 AM - Engine fired
4:30 AM - Car on ground
5:45 AM - Set up finished
6:45 AM - Race strategy meeting
8:15 AM - Warmup / Practice Session
-
-
That's truly amazing.
They should have a race where the teams show up with no assembled car and they have to put the car together and complete a lap within a 24hour period.